Central Petroleum Drills Northern Territory Gas Well With Commissioning Expected in October

MT Newswires Live
Yesterday

Central Petroleum (ASX:CTP) drilled the PV14 well in the Northern Territory to a total measured depth of 2,942 meters, equivalent to a true vertical depth of 2,096 meters, according to a Thursday filing with the Australian bourse.

The well is expected to be tied into the Palm Valley production facility and commissioned by the end of October, per the filing.

The well was tested for 90 minutes and reached a final estimated gas rate of about 3.2 terajoules per day, with no water or oil recovered. However, the company said the gas rate did not stabilize after 90 minutes and was still "increasing slowly" following the short-duration flow test.

PV14 is part of a joint venture between Central Petroleum with a 50% stake, Echelon Resources (ASX:ECH) with a 35% interest, and Cue Energy Resources (ASX:CUE) holding the remaining 15%.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.

Most Discussed

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10